The Challenge
To install a new floor that was strong enough and smooth enough for the construction company to convert the old building into a more useable space.
Our Solution
The solution provided was a liquid floor screed that would provide them with smooth floors to enable them to re-build the walls and carry on with their construction.
Results & Benefits
The floors were laid in one day which allowed the client to get back in on the screed 24/48 hours after to carry on with other tasks.